Works on three projects to improve water supply in Cork city nearing completion

The delivery of these projects is in addition to the ongoing upgrades at the Lee Road Water Treatment Plant
Works on three projects to improve water supply in Cork city nearing completion

The overall scheme is on schedule to be completed in early 2023 with construction works for the Eastern Strategic Trunk Watermain to be completed by Autumn 2022. Image: Irish Water

WORKS on three major projects to improve the security of the water supply in Cork city are near completion, with construction due to finish in early 2023, according to Irish Water.

The utility company, in partnership with Cork City Council, is progressing works on the Cork City Water Supply Scheme which includes the construction of additional strategic watermains, replacement of existing watermains and upgrades to multiple pumping stations supplying drinking water from the Lee Road Water Treatment Plant (WTP).

The delivery of these projects is in addition to the ongoing upgrades at the Lee Road Water Treatment Plant.

In a project update, Irish Water said that works on section one, the Eastern Strategic Trunk Watermain, are continuing.

These works involve upgrading 2.4kms of trunk watermains between Camden Quay and the Shanakiel Reservoir to increase the security of supply and reduce leakage of these large strategic mains. Pipe laying and ancillary works are progressing as planned.

Works on the Cork City Water Supply Scheme commenced in 2021 and are currently ongoing: Section one, the Eastern Strategic Trunk Watermain, involves upgrading 2.4kms of trunk watermains between Camden Quay and the Shanakiel Reservoir to increase the security of supply and reduce leakage of these large strategic mains. Image: Irish Water
Works on the Cork City Water Supply Scheme commenced in 2021 and are currently ongoing: Section one, the Eastern Strategic Trunk Watermain, involves upgrading 2.4kms of trunk watermains between Camden Quay and the Shanakiel Reservoir to increase the security of supply and reduce leakage of these large strategic mains. Image: Irish Water

Section two, the Western Trunk watermain, involves the construction of 5.5km of new trunk watermain that will link water supplies in the city centre and Cork harbour area.

Irish Water said that this watermain is the crucial provider of the additional water supply capacity to Cork city that will support growth and development and that the pipe laying works between the Lee Road WTP and Curraheen are nearing completion.

Section three, the Shanakiel Watermains Upgrades, involves upgrading the water supply network serving the north side of the city and includes the replacement of existing water mains and the construction of two new pumping stations.

The company said that approximately 80 per cent of the pipelaying works have been completed to date and works are ongoing at the two new pumping stations at the Shanakiel Reservoir site and adjacent to the Harbour View reservoir site, with the structures near completion.

It said that the overall scheme is on schedule to be completed in early 2023 with construction works for both the Eastern Strategic Trunk Watermain and Western Trunk Watermain to be completed by Autumn 2022.

Speaking about the project, Sean Twohig from Irish Water, said: “We are making great progress with the Cork City Water Supply Scheme. Together the three projects will increase the security of the drinking water supply, reduce leakage, increase capacity and enable the growth and development of the city. It will also result in improved energy efficiency across the city’s water treatment plants and networks.

The Western Trunk watermain, involves the construction of 5.5km of new trunk watermain that will link water supplies in the City Centre and Cork Harbour area. Image: Irish Water
The Western Trunk watermain, involves the construction of 5.5km of new trunk watermain that will link water supplies in the City Centre and Cork Harbour area. Image: Irish Water

“Together with our contractors for this project, Farrans Construction, we continue to liaise with all of the relevant stakeholders in the community. Throughout the project, we have tried to keep everyone as informed as possible by issuing weekly updates to elected representatives. I want to thank everyone for their patience so far as we work towards delivering this vital project that will provide a more reliable water supply and support the growth of Cork city."

Read More

Water supply restored to hundreds of people in Cork following completion of essential works at treatment plant

More in this section

St. Patrick’s Weekend Bank Holiday appeal from The RSA and An Garda Síochána Rise in drink and drug driving arrests prompts call for increased garda presence on Cork roads  
Test results due on dead birds removed from The Lough  ‘next week’ Test results due on dead birds removed from The Lough  ‘next week’
Key in Jail Cell Door Cork man who robbed 'terrified' students in school locker room jailed  

Sponsored Content

Vhi invests in youth projects to manage anxiety and build resilience Vhi invests in youth projects to manage anxiety and build resilience
Shared waters, shared futures Shared waters, shared futures
When the weather is part of the plan – The model that inspires European rugby When the weather is part of the plan – The model that inspires European rugby
Contact Us Cookie Policy Privacy Policy Terms and Conditions

© Examiner Echo Group Limited

Add Echolive.ie to your home screen - easy access to Cork news, views, sport and more