Key part of EirGrid’s cable works completed in Cork

EirGrid, the operator and developer of Ireland’s electricity grid, has welcomed the news, and said that nearshore works and ducting across the carpark should be completed shortly.
Key part of EirGrid’s cable works completed in Cork

Essential onshore cable ducting works on the Celtic Interconnector project crossing Claycastle Beach in Youghal have been successfully completed.

EirGrid, the operator and developer of Ireland’s electricity grid, has welcomed the news, and said that nearshore works and ducting across the carpark should be completed shortly.

The latest works mark a key step in preparation for cable installation commencement later this year for the subsea link, connecting the electricity grids of Ireland and France.

The Youghal works, which took place over the weekend, involved ducting pipes being lifted to the trench by five separate cranes, before being lowered into place.

The works were carried out between tidal windows at the beach.

This ducting will now be buried using material previously excavated from the beach, ensuring they are ready to receive the marine cable which is to be laid from France and into Irish waters in the next stage.

The beach will be fully reinstated following the completion of the installation works.

Michael Mahon, the chief infrastructure officer for the project, said that collaborative efforts of all stakeholders — including local authorities and community representatives — have played a crucial role in reaching this milestone.

“The success of this phase of works is a testament to the expertise and dedication of the entire project team — including engineers, contractors, and project partners from both countries,” he said.

“The patience and support of the local community of Youghal has also been invaluable, ensuring that the work could be completed efficiently and safely.”

Meanwhile, progress is also being made on other aspects of the energy project.

This includes works at the converter station site at Ballyadam, near Carrigtwohill, where cladding and internal fit-outs of buildings are taking place.

The converter station is where high voltage direct current (HVDC) is converted to high voltage alternating current (HVAC) for use on the Irish grid.

On the HVAC cable route between Carrigtwohill and Knockraha, jointing, backfilling, and road reinstatement continues with passing bay removal nearing completion.

On the HVDC route, trenching and ducting works are continuing on the N25 between Killeagh and Youghal.

Coinciding with works reaching a mid-way point, applications for the second phase of the €2.4m fund are currently being considered — with €841,013 in funding available to eligible communities and voluntary groups.

Read More

Archaeological dig to get underway at Cork beach this month 

More in this section

UAE-IRAN-ISRAEL-US-CONFLICT Cork travel agent creates flights ‘crisis team’ to get customers out of Middle East
Close up of doctor woman hands typing on laptop siting on a desk at the office Cork health jobs at risk over delays with permits
Visitor restrictions at CUH due to vomiting bug outbreak Visitor restrictions at CUH due to vomiting bug outbreak

Sponsored Content

The power of the G licence The power of the G licence
Happy couple receiving new house keys from real estate agent Time to get to grips with changes in rental laws
Boatbuilder turned engineer proves alternative paths can lead to success Boatbuilder turned engineer proves alternative paths can lead to success
Contact Us Cookie Policy Privacy Policy Terms and Conditions

© Examiner Echo Group Limited

Add Echolive.ie to your home screen - easy access to Cork news, views, sport and more