Coolglass awarded 50% of legal costs in landmark Supreme Court challenge

Coolglass wants to build the 13-turbine farm at Timahoe, Co Laois, in a location 2km from the Kilkenny border and 11km southeast of Portlaoise.
Coolglass awarded 50% of legal costs in landmark Supreme Court challenge

High Court Reporter

A wind farm developer has been awarded 50 per cent of its legal costs incurred in a landmark Supreme Court challenge related to climate law obligations of planning authorities and public bodies.

Last month, the seven-judge court upheld a High Court order that overturned An Coimisiún Pleanála’s (ACP) 2024 refusal of planning permission for Coolglass Wind Farm Ltd’s project, but for reasons different and narrower than those cited by the lower court.

The ruling made it clear that climate obligations were “real, effective, and if necessary enforceable” and created a “legal standard which must be complied with by a relevant body”.

Such obligations were binding on bodies with no planning function and bodies “not normally concerned with issues of climate change”.

Coolglass wants to build the 13-turbine farm at Timahoe, Co Laois, in a location 2km from the Kilkenny border and 11km southeast of Portlaoise.

In light of the ruling, the matter will be returned for consideration by ACP, formerly An Bord Pleanála.

In a judgment on the case’s legal costs published on Monday, the Supreme Court said it could not be said that Coolglass was “entirely successful” in its appeal, as several grounds of its case were rejected.

The court noted that while Coolglass succeeded in the “most important” aspect of the case, ACP prevailed in the majority of the grounds of appeal advanced by the developer.

In those circumstances, the court said it was appropriate to award Coolgass 50 per cent of its costs incurred in the appeal and previous High Court challenge against ACP.

The court made no order for costs against the Attorney General, who was also a party to the case.

More in this section

ULSTER Guide 75% of Irish adults say tourism has negative impacts on their local area
Electricity prices could rise by 8%, minister warns Electricity prices could rise by 8%, minister warns
Seven TDs and senators made over €7k of ineligible expenses claims in 2023, audit finds Seven TDs and senators made over €7k of ineligible expenses claims in 2023, audit finds

Sponsored Content

AF The College Green Hotel Dublin March 2026 The College Green Hotel: A refined address in the heart of Dublin
SETU and Glassworks set to accelerate innovation SETU and Glassworks set to accelerate innovation
Driving Growth in Munster: How property finance is powering Cork’s future Driving Growth in Munster: How property finance is powering Cork’s future
Contact Us Cookie Policy Privacy Policy Terms and Conditions

© Examiner Echo Group Limited

Add Echolive.ie to your home screen - easy access to Cork news, views, sport and more