The presence of horses on lands in Co Tipperary is holding up the construction of 114 new residential units, the High Court has heard.

Crann Ard Developments Ltd claims it is the owner of land located at Ardgeeha Upper, Clonmel, Co Tipperary, where it wants to build housing which is worth an estimated gross development value of €55 million, the court heard.

The firm claims that it is unable to commence work because William Reilly has left his horses on the land.

The company claims that Mr Reilly does not have permission to keep livestock on its land and is trespassing.

He has also failed to comply with its requests to remove his animals from the land, the company also claims.

As a result, the company is seeking various orders against Mr Reilly, of Haywood Road, Clonmel, including an injunction restraining him from entering or interfering with the plaintiff's lands.

It also seeks orders restraining the defendant from blocking or impeding access to the land, and that he remove all livestock he owns from the lands.

At the High Court on Friday, Frederick Gilligan BL, for the company, said his client had received a letter from solicitors acting for the defendant, alleging that Mr Reilly has been in continuous and exclusive possession of the lands since 2007.

Mr Gilligan said his side was aware that previous owners of the land had allowed Mr Reilly to use the land for a period, but rejected any claim that the defendant has any entitlement to use of occupied lands the company purchased several years ago with a view to developing into housing.

It is claimed that when agents of the company entered the lands last month, to carry out survey land, they found two horses on the land.

It is also alleged that an individual approached the company's agents and told them that the owner of the horses would not allow the works to take place peacefully.

The agents informed the company that they were not in a position to commence any building work until the property is cleared of all livestock.

The company said it wanted to commence groundwork on the site in August and September, but fears it will be unable to do so unless the court intervenes.

It is concerned about the financial impact on the firm due to any delay in commencing the construction works.

The matter came before Mr Justice Mark Sanfey on Friday.

The judge on an ex-parte basis granted the company permission to serve short notice of the injunction proceedings on the defendant.

The matter will return before the High Court next week.

More in this section

US import tariffs Drinks sector ‘next major priority’ for EU on tariff talks
Conor McGregor court case McGregor co-defendant James Lawrence sues Nikita Hand in the High Court
Ashling Murphy death Man (27) charged with assaulting garda during drug search

Sponsored Content

Dell Technologies Forum to empower Irish organisations harness AI innovation this September Dell Technologies Forum to empower Irish organisations harness AI innovation this September
The New Levl Fitness Studio - Now open at Douglas Court The New Levl Fitness Studio - Now open at Douglas Court
World-class fertility care is available in Cork at the Sims IVF World-class fertility care is available in Cork at the Sims IVF
Contact Us Cookie Policy Privacy Policy Terms and Conditions

© Examiner Echo Group Limited

Add Echolive.ie to your home screen - easy access to Cork news, views, sport and more