Minister ‘hopeful’ MetroLink planning will not be challenged

Various Metro projects for the capital have been proposed in recent decades, but none has yet proceeded to build stage.
Minister ‘hopeful’ MetroLink planning will not be challenged

By Cillian Sherlock, PA

The Transport Minister is “hopeful” that no legal challenge will delay a planned commencement of the MetroLink in 2027, after the multibillion-euro project was granted planning permission.

The 18.8km MetroLink rail line, most of which will be underground, is to run from north of Swords, through Dublin Airport, and down to Charlemont in the south of Dublin city centre at an estimated cost of €11 billion.

An Coimisiun Pleanala decided to grant permission generally in accordance with an inspector’s recommendation, which is contained in a 1,600-page report.

In granting the railway order, it also allows for the compulsory acquisition of land for the project.

Various Metro projects for the capital have been proposed in recent decades, but none has yet proceeded to build stage – despite more than €100 million being spent on those planned routes.

When operations begin, there will be trains every three minutes during peak periods.

The approval was welcomed by Minister for Transport Darragh O’Brien, who will bring proposals to Government for the establishment of MetroLink as a statutory delivery body responsible for the construction of the project.

The project is the largest single investment project in the National Development Plan.

Mr O’Brien said: “Today’s planning news is a hugely positive step for MetroLink, which is a key strategic project for the Government and Ireland.”

He said MetroLink will be transformative for the people of North Dublin and the entire country.

He added: “MetroLink will provide a fast, high-capacity, high-frequency public transport route, and it will enable the construction of tens of thousands of new homes.”

The Railway Order authorises all necessary works for the construction of MetroLink.

The journey time from Swords to the city centre is expected to last approximately 25 minutes.

Later, speaking on RTÉ’s News At One, Mr O’Brien said he was “hopeful” that there would be no legal challenge to the project.

“The planning permission is very positive, and hopefully it won’t be challenged,” he said.

He said work could commence “from 2027” but a challenge could delay the project.

He added that an expected “seven or eight-year” development could see the line open and operational by 2034 or 2035.

More in this section

Bruna Fonseca strangled after she went to ex's apartment to FaceTime her dog in Brazil, trial hears Bruna Fonseca strangled after she went to ex's apartment to FaceTime her dog in Brazil, trial hears
Gerry Hutch court case Leitrim barber jailed for seven years for rape of woman in his home
Mother of Keane Mulready-Woods tells court of ‘unimaginable cruelty’ after son’s murder Mother of Keane Mulready-Woods tells court of ‘unimaginable cruelty’ after son’s murder

Sponsored Content

Turning risk into reward: Top business risks in 2026 Turning risk into reward: Top business risks in 2026
Top tips to protect Ireland's plant health Top tips to protect Ireland's plant health
River Boyne in County Meath, Ireland. Water matters: protecting Ireland’s most precious resource
Contact Us Cookie Policy Privacy Policy Terms and Conditions

© Examiner Echo Group Limited

Add Echolive.ie to your home screen - easy access to Cork news, views, sport and more