Developer challenges decision to refuse permission for land hit with RZLT tax

The Residential Zoned Land Tax (RZLT) was introduced in the Finance Act 2021. The tax is an annual tax calculated at a rate of 3 per cent of the market value of land.
Developer challenges decision to refuse permission for land hit with RZLT tax

High Court reporters

A decision to refuse planning permission on account of a site being insufficiently serviced is “irrational” given it was hit with a tax applicable to ready-to-develop lands, a building firm has alleged in the High Court.

The Residential Zoned Land Tax (RZLT) was introduced in the Finance Act 2021. The tax is an annual tax calculated at a rate of 3 per cent of the market value of land.

Jolview Limited says An Bord Pleanála has on the one hand determined there are no capacity issues or other impediments to the development of its lands at Holmpatrick, Rush Road, Skerries, thus making it liable for the Residential Zoned Land Tax (RZLT).

The developer says the board, in considering whether to apply for RZLT, took into account the relevant infrastructure and servicing of the site and its suitability for residential development.

On the other hand, it says, the board later refused to grant it permission to build 18 houses on the greenfield site about 2km from Skerries town centre based on a report from its inspector that found there were “insufficient services and facilities” to support future occupants of the proposed development.

The board also found residential development on the site would be contrary to the Fingal Development Plan, it says.

The Drogheda-based company is asking the High Court to find that the planning refusal is “contrary to natural justice” and that the board is bound by its decision of last February to apply the RZLT to the site.

It says the planning refusal is invalidated by the board’s failure to have regard to its earlier tax decision and by its misinterpretation of the Fingal Development Plan.

The company notes the RZLT decision cannot guarantee a grant of planning development for any residential development on the site, but, it claims, An Board Pleanála cannot revisit or reconsider its earlier determination that the site is suitable for residential development in principle.

The developer also maintains that sections of the Taxes Consolidation Act, which underpins the RZLT scheme, contravene articles of the Constitution as an “unjust and disproportionate attack” on the company’s private property rights.

The RZLT levy, set at 3 per cent of a site’s value, was introduced in the 2022 budget in an attempt to encourage “the use of land for building homes”. It was due to apply to eligible lands from last February, but the Minister for Finance has delayed its activation by one year.

The case came before Mr Justice Richard Humphreys this week.

The developer’s senior counsel, Jarlath Ryan, instructed by Vincent Hoey & Company Solicitors, was granted permission to continue with the High Court judicial review proceedings against An Bord Pleanála, which has not yet had

More in this section

Bank of Ireland branches due to close Bank worker who stole €200k and tried to set branch on fire should have been jailed, DPP argues
Girls in single sex schools want more options to study STEM subjects, report shows Girls in single sex schools want more options to study STEM subjects, report shows
Wicklow man branded a 'monster' sentenced to three years for indecent assault of young girl Wicklow man branded a 'monster' sentenced to three years for indecent assault of young girl

Sponsored Content

Every stone tells a story Every stone tells a story
Absolute Property – Over a quarter century of property expertise Absolute Property – Over a quarter century of property expertise
Stay Radisson: Stay Sligo, Limerick, Athlone and Cork Stay Radisson: Stay Sligo, Limerick, Athlone and Cork
Contact Us Cookie Policy Privacy Policy Terms and Conditions

© Examiner Echo Group Limited

Add Echolive.ie to your home screen - easy access to Cork news, views, sport and more