National Children’s Hospital cost rises to over €2bn, Donnelly confirms

Minister for Health Stephen Donnelly has appealed to the contractor to stick to the construction deadline
National Children’s Hospital cost rises to over €2bn, Donnelly confirms

Vivienne Clarke

It will be April or May 2025 before the first patients can be admitted to the new National Children’s Hospital, but only if the contractor BAM “meets its own deadline” of completion by October 29th, 2024, Minister for Health Stephen Donnelly has said.

Speaking on RTÉ radio’s News at One, Mr Donnelly appealed to the contractor to stick to the deadline.

The estimated cost of the project has now increased to €2.24 billion after the Cabinet approved an additional €512 million in funds for the completion of the hospital on Tuesday.

However, stressing the need for the new hospital, Mr Donnelly said it will be “transformative” when it opens.

The Minister was also adamant that none of the additional money will go towards claims made by BAM for extra funds.

Of the €770 million claim by BAM, €645 million has been adjudicated, and less than 3 per cent awarded, he said, with the remaining €123 million yet to be adjudicated on.

It had been known since 2019 that the cost of the hospital was going to be higher than the original figure, with additional costs identified as the project progressed.

Since then, the combination of the Covid pandemic and the war in Ukraine has “significant increased building inflation and those costs fall to the State,” the Minister said.

Mr Donnelly acknowledged that the contractor could take further legal action in relation to costs, but as far as the Government is concerned, the additional funding approved by Cabinet was the final cost.

Frustration

The delays and escalating cost of the hospital had been “very frustrating for the Government”, Mr Donnelly said, adding the matter had also been frustrating for the previous government.

“This is an expensive hospital, it is an expensive design, it is on an expensive size. It is not the most expensive hospital in the world, but there is a lot of money that Irish people are paying.

“What I would say is, if there is a silver lining to that, is we are getting a huge amount in return for that money in terms of children's health care. This is going to be transformative,” Mr Donnelly said.

The completion date submitted by the contractor would only be met “if the contractor fully resources this project,” he cautioned.

“And you'll be aware of the board's comments previously that the contractor had not, in their opinion, fully resourced this project. I have a call directly to the contractor, and we want to get children treated in this hospital.

“It is literally night and day in terms of the future of children's health care.”

Timeline

Asked when the first child would be treated in the new hospital, Mr Donnelly replied: “If BAM meets its own schedule, I would implore BAM to fully resource this and do this, and that would be the end of October, there's then a six-month commissioning phase.”

Mr Donnelly said he took no comfort in having to appeal to the contractor to meet the deadline.

The additional funds approved by Cabinet on Tuesday was partly from the Department of Health’s capital budget, he explained, but added that it would not mean that other projects will not go ahead, as contingency plans had been made for this funding.

“There are no projects that won't go ahead,” the Minister reiterated.

“In advance of anticipation of this, the annual health budget for capital has gone well up by several hundred million a year. So it has been anticipated that this kind of an amount would be required.

“So there are that, not only are there projects not being affected by this. We're being more ambitious in terms of primary care centres as surgical hubs, more community beds, more acute beds this year.”

More in this section

Ashling Murphy death Man (27) charged with assaulting garda during drug search
British-Irish Intergovernmental Conference New Troubles legacy framework ‘effectively there’, says Harris
Eamon De Valera 50th anniversary Kelleher and Gavin to go head-to-head for Fianna Fáil presidential nomination

Sponsored Content

Dell Technologies Forum to empower Irish organisations harness AI innovation this September Dell Technologies Forum to empower Irish organisations harness AI innovation this September
The New Levl Fitness Studio - Now open at Douglas Court The New Levl Fitness Studio - Now open at Douglas Court
World-class fertility care is available in Cork at the Sims IVF World-class fertility care is available in Cork at the Sims IVF
Contact Us Cookie Policy Privacy Policy Terms and Conditions

© Examiner Echo Group Limited

Add Echolive.ie to your home screen - easy access to Cork news, views, sport and more