An Bord Pleanála conceds in challenge to refusal of Carlow wind farm

The proposal for seven turbines measuring 583 feet met significant local opposition and was first refused by Carlow County Council and then by An Bord Pleanála on appeal.
An Bord Pleanála conceds in challenge to refusal of Carlow wind farm

High Court Reporters

Coillte’s plan for an industrial wind farm in Co Carlow’s Blackstairs Mountains has found a second wind after An Bord Pleanála decided to concede in a High Court challenge to its planning refusal.

Futurenergy, a joint venture between the state-owned Coillte and the Electricity Supply Board (ESB), claimed the board’s decision to refuse permission for the seven-turbine development at Croaghaun Hill was “invalid” due to several alleged errors.

The proposal for seven turbines measuring 583 feet met significant local opposition and was first refused by Carlow County Council and then by An Bord Pleanála on appeal.

Futurenergy sought judicial review from the High Court, which this week was told the board was consenting to an order overturning its refusal.

Stephen Dodd SC, with John Kenny BL, for Futurenergy, said the board was also agreeing to consider the application afresh.
Mr Justice Richard Humphreys congratulated the parties and agreed to make the orders sought.

Carlow County Council had received more than 280 third-party submissions over the 38.5MW wind farm plan.

Futurenergy appealed to An Bord Pleanála as a first party, while third-party appeals were lodged by the Irish Hang Gliding and Paragliding Association, the Save Mount Leinster group and three individuals asking that the grounds for refusal be strengthened. The board received a total of 141 observations.

An Bord Pleanála ruled the wind farm proposed for a 246-hectare site should be refused as it contravened the Carlow County Development Plan.

It said the proposed site was within the designated Blackstairs and Mount Leinster Uplands Landscape Character Area, where wind farm development would not normally be permitted.

Among Futurenergy’s claims before the High Court was that the board relied on a new iteration of the Carlow development plan that came into force after this planning application and that it did not comply with a section of the Climate Action and Low Carbon Development Act of 2015.

Futurenergy also alleged irrelevant matters were taken into account in refusing the project.

The basis for An Bord Pleanála’s concession was not disclosed to the court.

Coillte was set to pay €5 million into a community fund over 35 years as part of the project. It said its project would power 25,500 homes each year.

More in this section

ULSTER Guide 75% of Irish adults say tourism has negative impacts on their local area
Electricity prices could rise by 8%, minister warns Electricity prices could rise by 8%, minister warns
Seven TDs and senators made over €7k of ineligible expenses claims in 2023, audit finds Seven TDs and senators made over €7k of ineligible expenses claims in 2023, audit finds

Sponsored Content

AF The College Green Hotel Dublin March 2026 The College Green Hotel: A refined address in the heart of Dublin
SETU and Glassworks set to accelerate innovation SETU and Glassworks set to accelerate innovation
Driving Growth in Munster: How property finance is powering Cork’s future Driving Growth in Munster: How property finance is powering Cork’s future
Contact Us Cookie Policy Privacy Policy Terms and Conditions

© Examiner Echo Group Limited

Add Echolive.ie to your home screen - easy access to Cork news, views, sport and more