Northside of city sees three regeneration projects delayed

The delayed projects include CNWQR Knocknaheeny Phase 2B, 38 units that were initially supposed to be complete in the last quarter of 2023.
Northside of city sees three regeneration projects delayed

Data shows delays to one project that was due in the coming weeks, as well as two that have not yet started. Picture: Larry Cummins

Three Cork City Northwest Quarter Regeneration Plan (CWNQR) projects have been delayed over just two months.

Data provided by the Minister for Housing on the timeline for the full completion of the plan, an ongoing regeneration project in the Knocknaheeny area, shows delays to one project that was due in the coming weeks, as well as two that have not yet started.

A department spokesperson said: “Responsibility for the progression of individual projects and the associated delivery timelines lie with Cork City Council.” 

The delayed projects include the CNWQR Knocknaheeny Phase 2B, 38 units that were initially supposed to be complete in the last quarter of 2023.

This has since been pushed back to Q4 2024, then Q3 2025, and in May this year the estimated completion date was Q2 2026 – this has now been pushed back to Q4 of this year.

Phase 4F of the same project, which consists of 23 units in Knocknaheeny, has not yet started construction and is still at the pre planning stage.

It is due in Q4 2028, nearly a year later than the Q1 2028 date given initially and as recent as May this year.

Homes at pre-tender stage

Also delayed before even starting is Phase 1D East, which consists of 14 homes at pre-tender stage, initially due in Q4 2027, then pushed to Q1 2028 and now due in Q4 2028.

In total, there are three projects within the scheme completed, consisting of 117 units, including one which has been done since 2017.

Contracts have been awarded and teams are onsite for a further three projects consisting of 124 units, due to be completed this year and next while a further six schemes with a cumulative 139 housing units have not yet seen work start – completion on all is due in 2028.

The latest predicted completion dates and historical data against which delays are measured were provided to Sinn Féin TD Thomas Gould.

Mr Gould said: “For 20 years now, the Knocknaheeny Regeneration project has been met with nothing but delays. People have been left in unfit homes for decades while construction has happened at snail’s pace.

“I have yet to receive an update on the regeneration that doesn’t detail at least one delay.” 

Councillor Michelle Gould added: “The people of Knocknaheeny are sick and tired of broken promises and a timeline that is never delivered. We need to see delivery now.

“Pushing projects off until the end of 2028 in the hope that people will have forgotten that deadline by then isn’t good enough.”

Read More

more #Cork City Council articles

Farranree locals say they will chain themselves to trees if council insists on removing them Farranree locals say they will chain themselves to trees if council insists on removing them
Boxd Coffee owners disappointed at council refusal for popular Carrigrohane Rd driv-thru Boxd Coffee owners disappointed at council refusal for popular Carrigrohane Rd driv-thru
Cork marks 35th anniversary of Ukrainian Independence Day Cork marks 35th anniversary of Ukrainian Independence Day

More in this section

TOPSHOT-NEPAL-WEATHER-LANDSLIDE-FLOODS Cork's Nepalese community fund-raising after devastating floods on Tibetan border
Building stock Delivery of cost-rental homes for Cork's 'squeezed middle' set to plummet
Health minister should come to CUH and talk to doctors about staffing problems, consultant says Health minister should come to CUH and talk to doctors about staffing problems, consultant says

Sponsored Content

Global hit Circus Extreme brings ‘Rock It Out!’ to Cork and Dublin Global hit Circus Extreme brings ‘Rock It Out!’ to Cork and Dublin
Transform your career, your way: choose MTU part-time education Transform your career, your way: choose MTU part-time education
Keeping their house in order: How PSRA regulation has raised the bar for Ireland’s property services sector Keeping their house in order: How PSRA regulation has raised the bar for Ireland’s property services sector
Contact Us Cookie Policy Privacy Policy Terms and Conditions

© Examiner Echo Group Limited

Add Echolive.ie to your home screen - easy access to Cork news, views, sport and more