Planning lodged for new primary care centre in Cork 

The project is due to be completed by the end of 2026. 
Planning lodged for new primary care centre in Cork 

A spokesperson for Cork Kerry Community Healthcare warned that timelines around projects of this scale tend to be dependent on a number of variables.

A planning application has been lodged for a Cork primary care centre that was promised five years ago and which is now projected to be completed by the end of 2026.

News that Douglas was to get a primary care centre broke in April 2019, when Fianna Fáil councillor Mary Rose Desmond told The Echo that she was “pleased to receive confirmation from Cork Kerry Community Healthcare” that HSE Estates would, in the second quarter of that year, invite expressions of interest to build a centre.

Speaking to The Echo this week, Ms Desmond said the process had been stalled by the Covid-19 pandemic, but she had been working diligently in the interim.

“I’ve been working away with the HSE, keeping the pressure on, but also assisting in any way I can, and, in that time, they’ve gone through that process of identifying a partner-developer and a site, and that site has gone for planning now.

“Short of construction, it’s at the final stage, it’s the final hurdle, and I’m really delighted,” the Cork City South East councillor said.

“Douglas Woolen Mills is the site that has gone successfully through that process with the HSE and that planning application has now been lodged, so I look forward to seeing it go through that process and getting to construction as soon as possible.”

Ms Desmond added that the privately developed primary care centre, which will have the HSE as its main tenant, would be a major benefit to the Douglas community. “The aim of these services is to keep people out of hospital and to stop our over-reliance on hospital care,” Ms Desmond said.

A spokesperson for Cork Kerry Community Healthcare warned that timelines around projects of this scale tend to be dependent on a number of variables.

“For that reason, a timeline of up to 30 months allows for a sensible contingency timeframe and an expected completion date of Q4 2026,” they said.

Read More

 Covid cases increase in all areas of Cork

more Cork health articles

stretcher HSE says patients must plan for hospital discharge as Cork facilities remain busy
Funding allocated for new mental health in-patient unit in Cork Funding allocated for new mental health in-patient unit in Cork
Former Cork resort hotel to become Mercy Hospital rehabilitation centre Former Cork resort hotel to become Mercy Hospital rehabilitation centre

More in this section

Man charged with being one of three who kicked and threw homeless man down stairs of Cork rail station Man charged with being one of three who kicked and threw homeless man down stairs of Cork rail station
Preferred route for €500m Cork northern distributor road revealed Cork northern distributer road would ‘dump traffic’ on Glanmire, says councillor
Cork coastal group cleans up at ocean awards Cork coastal group cleans up at ocean awards

Sponsored Content

Skechers launch basketball footwear range ahead of partnership with UCC Demons Skechers launch basketball footwear range ahead of partnership with UCC Demons
The season’s showstopper The season’s showstopper
Businesses in Co Cork towns and villages open for Christmas season Businesses in Co Cork towns and villages open for Christmas season
Contact Us Cookie Policy Privacy Policy Terms and Conditions

© Examiner Echo Group Limited

Add Echolive.ie to your home screen - easy access to Cork news, views, sport and more